Shattered Aspirations: A Journey Cut Short

IO_AdminAfrica16 hours ago4 Views

Rapid Summary

  • Bengaluru suburban Railway Project (BSRP): Approved in October 2020, designed to cater to 20 lakh daily commuters with modern air-conditioned trains across four corridors covering 148 km and 58 stations. Total cost: ₹15,767 crore.
  • Corridor Priorities: Corridor One (Majestic-Kempegowda International Airport), scheduled for completion by October 2023, but delayed alongside the full project deadline of october 2026.
  • Delays and Setbacks:

– Only ~18.5% progress achieved as of August 25,2025,with ₹1,992.9 crore spent.
– L&T terminated contracts for Corridor Two and Four citing disagreements over pricing models-notable criticism from implementing agency K-RIDE ensued.
– Land acquisition nearly complete at 97.75%, but execution issues stem from insufficient resource mobilization and contractor disputes.

  • Institutional Challenges:

– Diffused accountability due to dual governance by state (Infrastructure Department) and Central government agencies like K-RIDE and South Western Railway (SWR).- Bureaucratic tussles over leadership appointments for K-RIDE’s Managing Director position slowed decision-making further.

  • Citizen Concerns: Activists express frustration over lack of political urgency or consistent monitoring; similarity drawn with Namma Metro’s progress despite delays.

0 Votes: 0 Upvotes, 0 Downvotes (0 Points)

Leave a reply

Recent Comments

No comments to show.

Stay Informed With the Latest & Most Important News

I consent to receive newsletter via email. For further information, please review our Privacy Policy

Advertisement

Loading Next Post...
Follow
Sign In/Sign Up Sidebar Search Trending 0 Cart
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...

Cart
Cart updating

ShopYour cart is currently is empty. You could visit our shop and start shopping.