Quick summary
- Project Overview: The long-awaited Namma Metro Blue Line in Bengaluru, officially called the ORR-Airport Metro Line, is scheduled for completion by December 2027.It consists of two sections: Phase 2A (Silk Board to K.R. Pura) and Phase 2B (K.R. Pura to Kempegowda International Airport).
- Length and Progress: Total length is 58.19 km; as of june 2025, construction progress stands at 52.5%.
- Design Details:
– Airport City station will be built at ground level.
– Airport Terminal station will be semi-underground (7-8 meters below surface).
– Driverless trains with luggage racks and advanced safety features will cater to air travelers.
- Cost & Approval Timeline: Project cost estimated at ₹14,788 crore; proposals approved in phases between 2017-2019; DPR prepared starting October 2016.
- Recent Updates:
– Construction on the K.R.Pura-Airport section resumed after a nine-month suspension due to an accident.- Inspection by BMRCL MD J. Ravishankar focused on key areas like railway crossings near Indian Air Force property and depot works.