Delays Mount as Financial Issues and Contractor Lapses Stall Suchitra-Kompally Flyover

IO_AdminAfrica6 hours ago8 Views

Quick Summary

  • Construction along National Highway 44 at the Suchitra-Kompally stretch has caused meaningful traffic disruptions due to dug-up service roads, dust, barricades, and diversions.
  • The project includes ₹933 crore infrastructure upgrades spanning 27 km with three elevated corridors, four underpasses, and service roads.
  • Two flyovers from Kompally to Kallakal are scheduled for completion by December 2025; the full project is targeted for June 2026.
  • Progress rates: Kompally-Suchitra stretch is at 51%, while Kompally Junction to Kallakal stands at 37%.
  • Delays have been attributed to fund release issues (six-month halt between March and August), heavy rains, encroachments removal challenges, tree translocations, and restricted working hours in city limits.
  • Safety lapses linked to construction led to an accident in March 2024; contractors were arrested for failing to install adequate signage or lighting.
  • Proposals date back as far as 2012 with initial detailed planning launched in 2017; current completion pace raises doubts about meeting targets.
  • Commuters report worsening congestion pushing vehicles into residential areas. Bowenpally-Kompally suffers severe jams during peak hours.

Indian Opinion Analysis

The delays affecting the NH-44 upgrade reflect broader challenges of urban infrastructure advancement in India.While policymakers aim for seamless connectivity towards Nagpur and northern regions through critical flyovers and underpasses funded by significant resources (₹933 crores), practical obstacles-encroachments removal, financial disbursement delays, weather interruptions-continue demanding longer timelines.Beyond structural implications are human costs: commuters regularly endure extensive traffic snarls that influence productivity and mental well-being. With stalled progress amplifying frustrations since its conception over a decade ago (2012), this project highlights governance gaps requiring increased accountability mechanisms without contractor inefficiencies or safety oversights.

From a transportation viewpoint alone-it offers hope of long-term relief but ongoing temporary disruptions underline missed planning foresight previously avoidable pressures remaining acute unchecked infrastructural strain across India’s metros

Read More: https://www.thehindu.com

0 Votes: 0 Upvotes, 0 Downvotes (0 Points)

Leave a reply

Recent Comments

No comments to show.

Stay Informed With the Latest & Most Important News

I consent to receive newsletter via email. For further information, please review our Privacy Policy

Advertisement

Loading Next Post...
Follow
Sign In/Sign Up Sidebar Search Trending 0 Cart
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...

Cart
Cart updating

ShopYour cart is currently is empty. You could visit our shop and start shopping.