Kochi Metro’s Pink Line Marks Milestone with First Pier Cap Near Infopark

IO_AdminAfrica2 hours ago2 Views

### Quick Summary
– The first pier cap for Kochi Metro’s Kakkanad extension (pink Line) was placed on pillar number 281 near Infopark on August 28,2025.- The pier cap,weighing 80 tonnes,was cast at Kochi Metro Rail Limited’s (KMRL) Kalamassery yard and launched using a heavy-duty crane.
– So far:
– *22 pillars* have been constructed.
– *898 piles*, *56 pier caps*, *64 U-girders*, and *30 I-girders* have been prepared at the casting yard.
– Efforts are ongoing to make up for delays in project execution.
– Revised deadlines:
– Five stations along the 11.20-km viaduct are to be completed by June 2026.
– All nine stations and the entire corridor will be operational by December 2026. Girder installation is set to begin in September near Infopark.
– concerns remain over land acquisition for stations at Chembumukku and Padamugal.- A ₹1,200-crore loan proposal from the Asian Infrastructure investment Bank (AIIB) is yet to be approved by the State government and forwarded to the Centre despite KMRL’s approval over a year ago. Delays in loan disbursement slowed work activity.

The first pier cap for the Kochi metro's Kakkanad extension being placed atop pillar number 281 near Infopark.

### indian Opinion Analysis
The launch of Kochi Metro’s Kakkanad extension signals gradual progress toward enhancing urban connectivity within one of kerala’s major IT hubs, potentially easing traffic congestion and improving access in areas like Infopark. However, recurring delays-including land acquisition challenges at key station sites like Chembumukku-and financial uncertainties regarding AIIB loans coudl jeopardize timely project completion.

given its capital-intensive nature, securing financing on schedule should remain a priority as prolonged uncertainty could escalate costs or adversely impact contractor timelines amid inflationary pressures. Additionally, broader systemic streamlining between KMRL stakeholders-spanning local governance frameworks-seems essential if such projects are effectively aligned with fixed deadlines moving forward.

Read more: [Link](#)

0 Votes: 0 Upvotes, 0 Downvotes (0 Points)

Leave a reply

Recent Comments

No comments to show.

Stay Informed With the Latest & Most Important News

I consent to receive newsletter via email. For further information, please review our Privacy Policy

Advertisement

Loading Next Post...
Follow
Sign In/Sign Up Sidebar Search Trending 0 Cart
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...

Cart
Cart updating

ShopYour cart is currently is empty. You could visit our shop and start shopping.