– Pilot phase meters installed at two government connections in Thiruvananthapuram and seven feeder meters in Kalamassery.
– First phase includes installation of approximately three lakh meters; 1.5 lakh single-phase meters will be installed at government offices.
– Transformer border meter installation by March 2026.
– HT consumer meter installation by August 2026.
The establishment of a specialized sub-division within KSEB reflects strategic intent towards improving efficiency and reliability in energy distribution through smart metering technology. This move emphasizes accountability across project phases-monitoring mechanisms are intended to ensure adherence to timelines and performance benchmarks under RDSS guidelines.
The phased CAPEX approach mitigates resistance arising from fiscal concerns regarding TOTEX-based implementation models.Given Kerala’s prioritization of digital infrastructure,this large-scale deployment of smart meters could enhance resource management capabilities while addressing long-standing issues such as power wastage or billing inaccuracies. With realistic deadlines extending into mid-decade, success depends on consistent project execution and effective stakeholder engagement.
For further details: Read More